Split a project into subprojects and categories

What this is for

A hierarchy lets you split an undertaking into smaller projects with their own tasks. Categories group main projects in the list, and a parent's summaries cover the whole branch.

How to get there

Choose Goals & Projects → Projects (/projects). The menu next to a project offers Add subproject and Edit.

Step by step

  1. Next to the parent project, open the menu and choose Add subproject.
  2. Choose New project, enter a Name and confirm with Create. If you want to move an existing project, choose Existing project, pick Project to assign and click Assign project.
  3. To change the parent, choose Edit, expand the additional options, set Parent project and click Save. No parent · main project moves the project to the main level.
  4. For a main project, choose a Category in the edit form and save. You open the Project categories catalog through Manage project categories in Settings.
  5. Expand a branch in the list. In the parent's details, turn on Include subprojects to include their tasks as well.

Fields and options

Option Behavior
Parent project One parent; the list excludes the project itself and its descendants.
Existing project Assigning keeps the tasks and settings of the moved project.
Category Category of a main project; the interface uses this name for project labels.
New category, Color Name and color in the Project categories window.
Project Color A new subproject initially takes the parent's color until you choose your own.
Work project Work classification, inherited from the parent project.
Include subprojects Extends the task scope in the details to descendants.

You can reorder subprojects by dragging them in the Project structure section in the parent's details. The parent's progress covers the branch's tasks; the work cycle is described in statuses.

Common mistakes / pitfalls

  • You cannot set a project as its own ancestor.
  • Choosing an existing subproject hides finished projects and projects already assigned directly to the selected parent.
  • After you set a parent, the project category field is cleared; do not assign a category to each subproject separately.
  • A repeated category name shows a conflict message.
  • Changing the parent of an existing project keeps its current color.